Arbitration clause stands extinguished where new contract causes novation of original contract

Want to write for our Blog?

We accept Rolling Submissions throughout the year so if you wish to write on the subject of Alternate Dispute Resolution, check out our submission guidelines and submit your manuscript. Our editorial team would be privileged to review your submission!

Petitioner: B. L. Kashyap and Sons Ltd.

Respondent: Mist Avenue Private Ltd.

Court: Hon’ble High Court of Delhi

Date: June 2, 2023

Coram: Hon’ble Mr. Justice Prateek Jalan

FACTS:-

  • The parties entered into a ‘Construction Agreement’ in November, 2014 for a construction project named ‘MIST’, in Noida, given to the petitioners by the respondents.
  • The said contract contained an arbitration clause by virtue of which the parties could appoint an arbitrator by mutual consent in case of any dispute arising out of the contract.
  • On October 8, 2015, certain disputes between the parties had been settled by way of a Memorandum of Understanding (MoU) which expressly provided that the ‘Construction Agreement’ stood cancelled, along with details of payments due from the respondents to the petitioners.
  • Upon non-payment of dues, the petitioners invoked the arbitration clause of the 2014 agreement, however the arbitrator concluded that the MoU amounted to the novation of the original agreement and a breach of the MoU will not revive the terms of the agreement.

ISSUE:-

  • Whether the MoU between the parties led to the Novation of construction agreement and the arbitration clause contained in it;
  • Whether the failure to abide by the terms of MoU, amount to the revival of the contract?
  • Whether this court Is empowered to review the decision taken by the arbitral tribunal under section 34 of the A&C act?

 

JUDGEMENT:-

  • The court while citing Union of India v. Kishorilal Gupta & Bros. held that in cases wherein an original contract is substituted by a new contract (in this case an MoU), the entire contract along with the arbitration clause perishes with it.
  • Further, the court held that the failure to fulfil the conditions of the MoU would not amount to the revival of the original contract.
  • While relying on the Ssangyong Engg. & Construction Co.Ltd v. NHAI, the court emphasized that it does not have the power to set aside a decision of an Arbitrator under Section 34 of the act unless it is patently illegal. The interpretation of the terms of a contract by an arbitrator can be interfered with only if the finding is found to be irrational and perverse.
  • The court u/s 34 is not empowered to interpret the clauses, they are a matter of contractual interpretation.
  • The relevant clause of the MoU providing for the cancellation of the agreement is independent of the fulfilment of conditions stated therein.

DISCLAIMER: The USLLS ADR Blog is for informational and education purposes only, and should not be considered as legal advice. The opinions expressed herein are those of the authors themselves, in their personal capacity and do not, in any way or manner, reflects the views of USLLS ADR Blog or the ADR Cell of USLLS, or any other organisation that the authors are presently or previous associated or employed with in any manner. No representations are made on the correctness and accuracy of the opinions expressed as it may vary over time. Third-party links on the posts are only provided for convenience and we take no responsibility for examining and evaluating such links. We are making the USLLS ADR Blog available in our effort to advance the understanding and discussion on issues of contemporary relevance to the dispute resolution laws of India. Legal advice should always be sought from qualified legal practitioners only.